Description
Adaptation of the rainwater collection network and the Val da Rio plants, following the authorization of the project in question by the competent bodies (PIOP and Veritas)
Economics
The cost of the work amounts to €7.5 million, of which €2.7 million financed by NASPA Funds and €4.8 million financed by the Fund pursuant to art. 18 bis law 84/94
Objective
Obtaining the new authorization for the discharge of rainwater from the 1st and 2nd rain, and to improve the treatment of rainwater before discharge,
Benefits
Passing of the provisional authorization phase for the discharge of 1st and 2nd rain water;
improvement of the system in order to reduce management costs related to cleaning the collection system;
rationalization of the plant for the purpose of delivery of the authorization title and management of portions of the plant to the various concessionaires;
reduction of management costs for the NASPA.
Work Plan
Residual duration: 21 months
November 2023
Notice Publication
March 2024
Start of Works
June 2025
Tests