Interventi di adeguamento funzionale del Ponte di Via Maestri del Lavoro Chioggia
Project

Description

The building represents the only road access route for heavy vehicles heading to the Port of Saloni and a second access route to reach the historic center of Chioggia. The construction dates back to the early 1990s, from which time no major maintenance interventions were carried out

Economics

The cost of the work amounts to €2.3 million, financed for €1.2 million by the “Fund pursuant to art. 18 bis law 84/94”

Objective

Structural and road requalification through maintenance and restoration of the damaged structural parts and reconstruction of the bituminous conglomerate paving, road joints, rainwater drainage system, road barriers, pedestrian parapets and vertical and horizontal signs

Benefits

Restoration of structures, interrupting the phenomenon of degradation of the reinforcing irons and avoiding more serious deterioration phenomena;

Making vehicular traffic safe by renovating road joints, paving and road barriers;

Making the side walkways safe by renovating the pedestrian parapets;

Work Plan

Residual duration: 18 months
Step 1
Design
Step 2
Tender (6 months)

March 2023
Notice Pubblication

Step 3
Execution of Works

September 2023
Start of Works

July 2024
Tests