Molo Sali – Sheet piling restoration works and completion of the quay port use

Molo Sali - Opere di ripristino palancolato e completamento banchina ad uso portuale
Geographical Framework
Molo Sali - Opere di ripristino palancolato e completamento banchina ad uso portuale
Project

Description

Restoration works of the perimeter sheet piling and completion of the quay structures in order to allow the construction of a rear yard in anticipation of future use for port activities.

Economics

The work benefits from financing of €16 million with DM 353 funds.

Objective

Allow the delivery operations of the sludge dredged from the canals, up to the planned project altitude of +1.50 m above sea level.

Benefits

Stabilize and safely maintain the canal side margins;

Allow sludge transfer activities;

Create additional yards and docks for an increase in port activities;

Increase in commercial traffic.

Work Plan

Residual duration: 18 months
Step 1
Design
Step 2
Tender (6 months)

Augusto 2022
Notice Publication

Step 3
Execution of Works (24 months)

March 2023
Start of Works

March 2025
Tests