![Molo Sali - Opere di ripristino palancolato e completamento banchina ad uso portuale](https://www.port.venice.it/wp-content/uploads/2023/09/molo-sali-ripristino-palancolato-e-completamento-banchina.png)
![Molo Sali - Opere di ripristino palancolato e completamento banchina ad uso portuale](https://www.port.venice.it/wp-content/uploads/2023/09/progetto-molo-sali-ripristino-palancolato-e-completamento-banchina.png)
Description
Restoration works of the perimeter sheet piling and completion of the quay structures in order to allow the construction of a rear yard in anticipation of future use for port activities.
Economics
The work benefits from financing of €16 million with DM 353 funds.
Objective
Allow the delivery operations of the sludge dredged from the canals, up to the planned project altitude of +1.50 m above sea level.
Benefits
Stabilize and safely maintain the canal side margins;
Allow sludge transfer activities;
Create additional yards and docks for an increase in port activities;
Increase in commercial traffic.
Work Plan
Residual duration: 18 months
Step 1
Design
Step 2
Tender (6 months)
Augusto 2022
Notice Publication
Step 3
Execution of Works (24 months)
March 2023
Start of Works
March 2025
Tests